Screen Reader Access Skip to Main Content Font Size   Increase Font size Normal Font Decrease Font size
Indian Railway main logo
Search :
Find us on Facebook   Find us on Twitter Find us on Youtube View Content in Hindi
National Emblem of India

About Us

Citizen Charter

Trains & Timings

Passenger Services / Freight Information

Public Information

Tenders

Contact Us

Press Releases
Applications & Bills Status
Vendor Registration
Vendor Login
Important Information
Results & Notifications
Other information
FREQUENTLY ASKED QUESTIONS BY VENDORS:
Status of SMS based Passenger Complaints
Downloads
Procedure & Application Forms
Appointment under Sports Quota
Appointment under Scouts & Guides Quota
Appointment under Cultural Quota
Waival of Demurrage and Wharfage
Guidelines & Instructions for Registration of Contractors/ Suppliers/ Vendors for expenditure contracts
Registration of Medical Pharmaceutical firms in Chief Medical Director-s Office, South Central Railway, Secunderabad
Registration of Private Hospitals for Health Care with South Central Railway
SOUTH CENTRAL RAILWAY- REGISTRATION POLICY
Public Information Regarding Train Accident
Train Accident Inquiry Reports
User Login for Vendor Registration
 
Bookmark Mail this page Print this page
QUICK LINKS
   

SOUTH CENTRAL RAILWAY
PRESS RELEASE
PUBLIC RELATIONS OFFICE, SECUNDERABAD - 500 071
No.713/2018-1902-01-2019
Secunderabad
Parbhani – Mudkhed Doubling Works on Fast Pace -New Boon to Rail Transportation in Marathwada


Development of Rail Transportation facilities in Marathwada region was a long cherished dream of the people. The project has been accorded priority by the Hon’ble Prime Minister’s office and being regularly monitored by Hon’ble Minister for Railways, Shri Piyush Goyal for early completion.

Doubling of Parbhani – Mudkhed existing line has been sanctioned in the Year 2012-13 for a distance of 81.4kms with an estimated cost of Rs 390.60 Crore. The expenditure incurred o­n this project during the last 3 years is Rs.244 Cr. Out of which Rs.55.03 Crore has been spent in the current financial year (i.e., April, 2018 to Nov, 2018).

Completed Sections:

ØOut of the proposed doubling work o­n a total of 81.4 Kms route from Parbhani to Mudkhed, the Railway line for a distance of 17 kms stretch between Parbhani and Mirkhal section has been commissioned in the Month of June, 2017.

ØOther stretch between Mudkhed - Mugat (9.3kms) has been completed along with certification of Commissioner of Railway Safety and commissioned for Train services o­n 10th October, 2018.

ØLimbagaon - Nanded - Maltekdi (14.10Km) section is also completed and commissioned o­n 17thOctober, 2018 to facilitate the Train movements for the convenience of passengers. With this out of 81.4 Kms total route, 40.4 Kms stretch has been completed.

Works under progress:

ØThe Balance section between Mirkhal – Limbagaon(30.9Kms) and Maltekdi – Mugat(10.0) for a total length of 41.00 KM section is targeted for completion by March, 2019.

Once the doubling project between Parbhani – Mudkhed completed, it would pave sound foundation for improving goods traffic and passenger traffic in Marathwada region in the near future and it will boost the industrial development also. While around 35-40 trains are currently passing o­n the rout with single line working, the train movements are expected to be increased significantly after the doubling work is completed. Parallel to the doubling works, the electrification of entire Nanded division is also taken up o­n full swing and targeted for completion in a span of three years.

All the Major works like land acquisition, cable works, construction of Major and Minor bridges, Road Under Bridges, Relay rooms and Cabins have been completed. Passenger amenities like high level plat forms, benches, water booths etc are completed at all the stations, except few track related minor works like insertion of glued joints, track lining etc. 3 minor bridges, o­ne Road Under Bridge works is o­n progress.  





  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.